How to pour warm floors using tees-2 technology

Please advise how to pour the warm floors in the mixture of a residential country house with a column foundation using tees-2 technology.

The sequence of your actions is as follows. Regardless of the composition of the soil on its surface, the sand-gravel mixture is poured and conscade with conscientiously. You have a pillow with a thickness of at least 200 mm, intended for drainage of moisture. Provide the removal of this moisture outside the perimeter of the house.

A plastic film is stacked over the pillow, the so-called loading plate is poured on top of which. It can be performed from a skinny concrete with a thickness of 5-7 cm. After drying, it is covered with bitumen waterproofing using bitumen mastic. Having created reliable protection against moisture, it is possible to engage in the insulation that you write about in your letter.

It is better to put the plates of the 10-centimeter thickness of extruded polystyrene foam. He has excellent thermal insulation properties plus it does not absorb moisture at all. The next layer of "cake" is a metal grid. If you decide to do heated floorThe grid is stacked (and tied) a metal-plastic tube in the form of a snake in the part of the floor you are going to warm up.

Then this pipe should be connected to the system of heating of a country house. Another metal mesh with cells of 50 × 50 mm from a wire with a thickness of 4-6 mm is stacked over the pipe over the pipe. Next, the plate is poured (concrete) with a thickness of 7-10 cm. To avoid subsequent cracks in the floor, it is advisable to perform all the fill in one pass, which will require the known voltage of the performers.