One of the final stages of construction of any building is a device blind area. It's not just a way to protect the building from rain water, and the foundations of subsidence, but also an important element of improvement of the adjacent territory. Usually, the device is proceeded after finishing the facade or at the end cap trim.

In order to justify the blind area its main purpose, it must be made of waterproof material with the observance of certain rules. Its correct device provides load shedding on the waterproofing underground part of the building and thus prolongs its life, why put it off it in the closet is not necessary.

Any blind area require preliminary training ground. No matter what material is expected to perform her cover, the soil should be cleaned from top soil and carefully compacted. This is especially important for a house built on heaving soils.

The device of the house of the house includes a device of the underlying layer and coatings. The underlying layer (for it you can use sand, clay, dropping, small crushed stone) is necessary to create a smooth compacted base for subsequent laying of the coating. The view of the underlying layer is selected depending on the type of top material. The layer thickness is usually selected20 cm. Concrete is used for coating, fine cobblestone, asphalt, paving slabs.

Proper device of the cabin around the house

In the trench around the house, sand falls asleep and thoroughly tram either watering water to seal. Crushed stone, gravel or broken bricks on top of the sand. This pillow is necessary to filter moisture, which can penetrate through the capillaries of the upper layer and, freezing, destroy the breakfast. It should be borne in mind that the construction trash for pillows cannot be used. With a high arrangement of groundwater between the layer of stone fractions and the sand, geotextiles should be laid, which will protect against casing.

The next step is the device of the selected type of coating. The depth of the trench should be calculated in advance so that the upper layer is not too thin. Along the trench at the outer edge, a removable formwork is installed. Instead of formwork, you can install a curb stone. If laying of concrete coating is planned, it is first necessary to make deformation-temperature seams that protect the concrete coating from the destruction of frosty winter. Deformational seams are the rails, put on the edge across the scene in a step of no more than 3m. Rake treated bitumen. Their upper surface should be at one level with the upper surface of the concrete, taking into account its slope. Then the concrete is stacked, the rails are served by the beacons for which it is leveling. The finished wet breakfast is sprinkled with cement, and then smooth the trim and cover with a wet cloth. During the week, the concrete is kept in such a state, periodically watering water so that the fabric is always wet. After a week, the device deficiency is completely completed.

When building, the scene should follow the following rules:

1. In order for the water to get away from the house, the scene is stacked with a bias from the building. The bias must be at least 2%. And although it is almost impaired, nevertheless guarantees the water lead from the base.

2. There is a gap between the breakdown and the wall to protect the walls from damage during the sediment of the scene. The compensation seam is filled with polystyrene foam, sand, polyurethane sealant. Sometimes two layers of rubberoid are sufficient.

3. On the perimeter of the scene digging grooves for drainage or laid special gutters that look much more aesthetic.

4. The width of the scene is accepted by 20 sshmir the projection of the roof of the roof on the ground, but not less than 60 cm.

If the device of the scene is performed with a violation of these rules, then, unfortunately, the consequences are already very soon found: cracks, chips, destruction of individual sections, which will adversely affect the conditions of operation of the building. The importance of the function that the scene performs, implies a responsible attitude to its device.